Dredging of Hudson for New Tappan Zee Bridge Begins

Hits: 140

WPCNR TAPPAN ZEE NEWS. From the New York State Thruway Authority. August 2, 2013:

Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use extreme caution within 1,000 feet of all construction barges as a safety precaution.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com.

Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being processed and properly disposed at offsite locations.

Impact Pile driving began this week as part of the ongoing test pile program and will continue over the next three months at various locations for future pile foundations. This work will be performed 7 a.m. to 7 p.m. on weekdays and at times on Saturdays from 12 noon to 7 p.m.  The test pile program will verify subsurface conditions test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Ongoing operations:

  • Test pile program
  • Rockland bulkhead construction (including fence & gates)
  • Dock Extension at Rockland (under existing bridge)
  • Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
  • Survey inspections on existing bridge
  • Rockland and Westchester environmental monitor installations
  • Geotechnical land borings
  • Mobilization at the exit 10 staging area
  • Support for river-based work from the Rockland shoreline

Westchester:

Limited test-boring operations will continue on Thruway property near the Irving Neighborhood in Tarrytown.  The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday, August 5 through Wednesday, August 6.

Rockland:

TZC, LLC will reconstruct the sidewalk along River Road in S. Nyack north of the existing bridge. This is part of the Bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday, August 5 and Tuesday, August 6. River Road will be limited to one lane with flag persons in place to control traffic safely.

Survey activity will occur in the southbound lanes of I-87/I-287 and will require a temporary lane closure between exit 10 and the existing bridge from 10 a.m. to 3 p.m. Monday, August 5 and Tuesday, August 6.

Posted in Uncategorized

More Barges to Come. Thruway Authority Adds Lights Beyond Coast Guard Requirements

Hits: 208

WPCNR TAPPAN ZEE BRIDGE CONSTRUCTION NEWS. From the New York State Thruway Authority. July 31, 2013:

The Thruway Authority issued this follow-up statement today: “The U.S. Coast Guard made it clear that the lights on the barge met all requirements and were visible for one nautical mile but, as an added precaution, extra lights were added immediately following this tragedy because we wanted to go above and beyond to try and prevent something like this from happening again,” according to Dan Weiller, Thruway Authority Spokesman.

Approximately 2 dozen barges of varying sizes are currently in the Hudson River as part of the project but the exact number changes almost daily. More are scheduled to arrive shortly to begin dredging.

—After the  incident after the Piermont barge crash last Friday, killing two passengers on a speed boat and injuring four others, dozens of extra LED solar/battery powered lights were added to all barges, moorings and other vessels as a precaution above and beyond US Coast Guard requirements

—At night the barges are in the fixed mooring locations, during the day they can be moved to get construction materials/supplies stored on them to active work areas

 

Posted in Uncategorized

City Will Audit Verizon and Cablevision Revenues

Hits: 434

WPCNR COMMON COUNCIL CHRONICLE EXAMINER. By John F. Bailey, July 31, 2013:

THE CITY OF WHITE PLAINS will audit cable franchise operators in the city, agreeing to authorize spending $35,000 to hire an independent audit firm with experience examingng cable operations, to audit Verizon Fios and Cablevision for the last five years of operations in the city. The new effort was presented to the Common Council at a Special Meeting Monday night.

 

John Callahan the city Corporation Counsel told WPCNR the effort is to confirm that Verizon and Cablevision are paying all the money they should on all the revenue streams they are supposed to be paying their franchise fees on.

 Callahan said that if the audit found Verizon and Cablevision are earning less, the city might have to pay a refund. However that is not likely. towns in the county have found in recent audits that they were owed amounts of approximately a million dollars by cable companies after similar audits.

The cable business has been losing share to new media.

Verizon has taken away about 4,000 subscribers from Verizon, which has 15,800, down about 4 to 5,000 from five years ago when Verizon came in. And the cable business is losing share to the new media. 

Callahan, asked about the Public Education Grants fees that cablevision has not paid in six years, told WPCNR  the city is negotiating with Cablevision on this matter. Estimates are the lack of an agreement on the PEG fee  has been costing the city cable television operation $220,000 a year for 9 years.

Establishing regular PEG payments again with Cablevision is critical for the city to pay for the $1.5 to $2 million move to the White Plains Public Library some day. They have no money to do that yet, unless other revenues are diverted to the reinvention of White Plains Public Access TV to the library.

 

Posted in Uncategorized

Speedboat Accident Aftermath: Kills fiancee of WP Teacher. Thruway Says Barge was properly legally Lit

Hits: 420

 

WPCNR EPITAPH. Statement from the New York State Thruway Authority. July 28, 2013: 

According to Gannett reports, the speedboat crash Friday evening into a close-to–the-water construction barge anchored off the south side of the present Tappan Zee Bridge, claimed the life  of Lindsey Stewart, 30, of fiancee of Brian Bond, also a passenger. Mr. Bond was seriously injured.  WPCNR notes Mr. Bond is a  teacher at White Plains Mamaroneck Avenue Elementrary School.

A third person, Mark Lennon,  was still missing and presumed dead. The man piloting the boat, JoJo John was being treated for injuries and has been charged by authorities, with vehicular manslaughter, three counts of vehicular assault.

The boat departed Piermont, a village on thr western Hudson River shore, south of the Tappan Zee Bridge at approximately 11 P.M., and crashed into a barge south of the bridge throwing passengers of the boat into the water apparently.

The New York State Thruway Authority issued this statement Saturday on the crash into its contractors’ barge, essential denying any possible negligence in lighting the barge and making it visible to mariners at night:

 “While the Rockland County Sheriff, N.Y. State Police and U.S. Coast Guard continue to investigate this tragic incident, the New York State Thruway Authority is conducting its own review of safety procedures on the Hudson River as part of the New NY Bridge Project. Our thoughts and prayers are with the victims and their families during this difficult time.”

“At this point, Tappan Zee Constructors, LLC (TZC) has reported to the Thruway Authority that all Coast Guard lighting requirements were met and that the barges were properly lit Friday night. All lighting was checked Saturday morning and is fully operational at all barge locations associated with the project.

Thruway and TZC have worked with the Army Corps of Engineers and Coast Guard to determine approved locations for the barges and appropriate information has been provided to be included in Notices to Mariners.

Impact pile driving originally scheduled for today (Saturday) has been temporarily suspended out of respect for the victims and to accommodate the investigation.”

Posted in Uncategorized

Bramson Discusses Trayvon Martin Death.Opposes Stand Your Ground Laws

Hits: 413

WPCNR LETTER TO THE EDITOR. July 28, 2013:

IMG_5925

NOAM BRAMSON IN WHITE PLAINS LAST WEEK.

Noam Bramson, candidate for County Executive authored this commentary on the Trayvon Martin shooting and death, and the verdict in the George Zimmerman trial in Sanford Florida, after attending a memorial for Martin Friday evening:

 

Last night, I attended a vigil in Peekskill held in memory of Trayvon Martin. It was a good event, attended by an impressive cross section of the surrounding community, and featuring speeches from religious and civic leaders. This morning, I feel inspired to share a few thoughts, but I do so with caution and humility, because I can’t claim any special or original wisdom on such a difficult subject.

As a father, I can only imagine the pain that Trayvon’s parents, Sybrina Fulton and Tracy Martin, must now feel. When a case is the topic of such extensive commentary and has such broad social significance, the person at its center can be reduced to an abstract symbol. It is important to remember that he was a human being, flesh and blood, loved and
now mourned.

As a policy-maker, I believe that so-called “Stand Your Ground” laws encourage a dangerous shoot-first mentality. Except in the rarest of circumstances, we are much better off working to deescalate conflict and leaving deadly force to public safety professionals. The success of the gun lobby in promoting these laws around the country offers a dispiriting parallel to the gun lobby’s equally harmful obstruction of common sense gun safety
standards in Congress and elsewhere. I genuinely respect the right of responsible citizens to keep and bear arms, but I will never comprehend the logic that says the answer to gun violence is more guns, with more firepower, in more hands.

Finally and most importantly, as a citizen, the verdict and the myriad discussions that followed remind me of how much race relations in America have advanced . . . and of how far we will still have to go.

Several years ago, as I was preparing to leave home to attend the annual  MLK breakfast in New Rochelle, I asked my boys, half-jokingly, what I should say to the crowd. Jeremy replied: “why don’t you talk about how people should be judged by the content of their character and not by the color of their skin.”

Jeremy had just learned about Dr. King in kindergarten and was simply repeating
the lesson, but, still, I was floored and moved. When a little white boy growing
up in the suburbs learns those words literally before learning how to add and
subtract, there is no doubt that something is going right.

But there is also a sort of false comfort in such little anecdotes. Knowing the words is
easier than living them. And celebrating equality in theory, although certainly a good thing, is no substitute for wrestling with the persistence of inequality, in all its uncomfortable complexity. Trayvon’s death and the disparate responses to the verdict, starkly divided by race, reveal a nation still struggling with its original sins. All of us need to try harder to reach beyond the confines of our own personal interests and experiences and better understand our neighbors and fellow Americans.

I am an optimist by nature, so I will close with another famous quote from King: “the arc of the moral universe is long, but it bends towards justice.”

Good words to remember. Let’s also remember that the arc of justice bends with our help.

My thanks to the organizers of last night’s (Friday)vigil for giving us a chance to come together.

Noam Bramson, Mayor, City of New Rochelle

Posted in Uncategorized

Attorney General Catches 3 White Plains Gas Stations Gouging Prices After Sandy

Hits: 376

WPCNR WHITE PLAINS LAW JOURNAL. From the Office of the New York State Attorney General. July 24, 2013:  
As part of his ongoing probe of high gasoline prices in the wake of Hurricane Sandy, Attorney General Eric T. Schneiderman today announced that he has reached a settlement with a major gasoline wholesaler and retailer that supplies and operates stations in the lower and mid-Hudson Valley. CPD Energy Corp. (“CPD”), based in New Paltz, has agreed to pay $50,000 in penalties for charging unconscionably excessive prices at six stations that it owns in Westchester, Putnam and Ulster counties.
The CPD settlement represents the largest penalty paid by a single operator for price gouging on gasoline after Hurricane Sandy.
Three of the gas stations are the Mobil Station at 1237 Mamaroneck Avenue in White Plains, and the popular Mobil at 174 Westchester Avenue and the Hutchinson Mobil Station on the Hutchinson River Parkway. Settlements were reached with the following White Plains stations
Mamaroneck Service, Inc. (Mobil), 1237 Mamaroneck Avenue, White Plains, NY
  • Difference between wholesale price and retail price prior to storm: $0.93
  • Difference between wholesale price and retail price immediately following storm: $1.17
  • Increase in wholesale/retail spread before-and-after the storm: 33%
  • Retail price immediately following the storm: $4.29
Chestnut Mart (Mobil), 174 Westchester Avenue, White Plains, NY
·         Price before the storm:  $4.33
·         Maximum price after the storm:  $5.03
·         Increase in price before-and-after the storm: $0.70
Hutchinson Parkway Station (Mobil), Hutchinson River Parkway, White Plains, NY
·         Price before the storm:  $4.25
·         Maximum price after the storm: $4.85
·         Increase in price before-and-after the storm: $0.60
“As thousands of New Yorkers sat in line for hours waiting to buy gasoline during the state of emergency created by Hurricane Sandy, some crooked station owners increased their retail prices by excessive and illegal amounts,” Attorney General Schneiderman said. “Today, we are continuing to send the message that ripping off the public during a time of crisis is against the law, and that those who engage in illegal price gouging will be held accountable.”
Attorney General Schneiderman also obtained a default judgment of $23,733 against another operator, Mena Inter Inc., doing business as a USA Petroleum gas station in Farmingdale. The judgment includes disgorgement of excess profits, civil penalties, and costs to the state, and represents the largest penalty assessed for gouging at a single station. The order was entered by the Honorable Norman Janowitz in State Supreme Court in Nassau County.
The Attorney General also reached monetary settlements with five additional station owners — two in Westchester, one in Rockland and two in Nassau — for violations of the New York State Price Gouging statute. These actions come on the heels of 30 previous settlements announced earlier this year, and bring the total penalties and costs paid to $287,618 by 42 gas stations found to have engaged in price gouging. The Attorney General sued two other gas stations in May. Those lawsuits are pending. Investigations of several other gas stations are ongoing.
In the days after the storm, areas of New York saw some of the largest jumps in gas prices in state history. The price jumps resulted in hundreds of complaints received by Attorney General Schneiderman’s office and showed that prices were changing at the pump, not only overnight but several times a day.
New York State’s Price Gouging Law (General Business Law § 396-r) prohibits merchants from taking unfair advantage of consumers by selling goods or services for an “unconscionably excessive price” during natural disasters. The price gouging law covers New York State vendors, retailers and suppliers. The law specifically says that a price may be considered excessive if there is a “gross disparity” between the prices charged immediately before and after the emergency and the disparity is not attributable to higher costs imposed upon the seller.
The following stations are covered by the CPD settlement:
(All prices below are for regular unleaded gasoline.)
 
Yorktown Food Mart Inc. (Mobil), 2035 Saw Mill River Road, Yorktown Heights, NY
·         Price before the storm: $4.13
·         Maximum price after the storm:  $4.67
·         Increase in price before-and-after the storm: $0.54
 
Chestnut Mart Inc. (Mobil), 838 Kimball Avenue, Yonkers, NY
·         Price before the storm:  $4.06
·         Maximum price after the storm:  $4.58
·         Increase in price before-and-after the storm:  $0.52
 
Friendly Service New Paltz (Mobil), 409 Main Street, New Paltz, NY
·         Price before the storm:  $4.00
·         Maximum price after the storm: 4.47
·         Increase in price before-and-after the storm:  $0.47
 
 
Chestnut Mart Inc. (Mobil), 3081 Route 22, Patterson, NY
·         Price before the storm:  $3.95
·         Maximum price after the storm:  $4.37
·         Increase in price before-and-after the storm:  $0.42
The price increases charged by CPD following Sandy at these six gas stations greatly exceeded CPD’s additional costs. Because Hurricane Sandy knocked power out to the area’s gas refineries, the regular supply terminal from which CPD purchased gasoline had either a limited supply available or none at all during the State of Emergency period. As a result, CPD bought gasoline from more distant terminals including Syracuse (Van Buren), Springfield, MA, Revere, MA, East Providence, RI and New Haven, CT, and incurred additional costs of approximately 16 cents per gallon to transport this gasoline to its stations. However, CPD’s price increases at the six stations—which ranged from 42 cents per gallon to as much as 70 cents per gallon—greatly exceeded the additional transportation costs.
The default judgment was entered against the following station:
(All prices below are for regular unleaded gasoline. The spread is the difference between the wholesale price paid by the operator and the price charged at the pump.)
Mena Inter Inc. (USA Petroleum), 630 Main Street, Farmingdale, NY.
  • Difference between wholesale price and retail price prior to storm: $1.04
  • Difference between wholesale price and retail price immediately following storm: $1.80
  • Increase in wholesale/retail spread before-and-after the storm: 73%
  • Retail price immediately following the storm: $4.59
Settlements were also reached with the following retail service stations:
(All prices below are for regular unleaded gasoline. The spread is the difference between the wholesale price paid by the operator and the price charged at the pump.)
Katonah Gas & Auto Service, Inc. (Mobil), 80 Bedford Road, Katonah, NY
  • Difference between wholesale price and retail price prior to storm: $1.26
  • Difference between wholesale price and retail price immediately following storm: $1.61
  • Increase in wholesale/retail spread before-and-after the storm: 27%
  • Retail price immediately following the storm: $4.79
A&Z Service Center (Citgo), 364 New Hempstead Road, New City, NY
  • Difference between wholesale price and retail price prior to storm: $0.85
  • Difference between wholesale price and retail price immediately following storm: $1.35
  • Increase in wholesale/retail spread before-and-after the storm: 58%
  • Retail price immediately following the storm: $4.39
ZAM Service Center (BP), 464 West Jericho Turnpike, Huntington, NY
  • Difference between wholesale price and retail price prior to storm: $0.87
  • Difference between wholesale price and retail price immediately following storm: $1.20
  • Increase in wholesale/retail spread before-and-after the storm: 48%
  • Retail price immediately following the storm: $4.30
The 900 Broadway, LLC. (BP Gas Station), 900 N. Broadway, Massapequa, NY
·         Difference between wholesale price and retail price prior to storm: $.78
·         Difference between wholesale price and retail price immediately following storm: $1.18
·         Increase in wholesale/retail spread before-and-after the storm: 51%
·         Retail price immediately following the storm: $4.29
For information about lawsuits filed and settlements reached previously by Attorney General Schneiderman related to Gas Gouging during the emergency, please click here.
The lawsuit against Mena Inter Inc., and the settlement with The 900 Broadway, LLC. were handled by Assistant Attorney General-in-Charge Valerie Singleton of the Nassau Regional Office, under the supervision of Executive Deputy Attorney General for Regional Affairs Martin J. Mack. The other settlements were handled by Assistant Attorney General Sandra Giorno-Tocco and Assistant Attorney General-in-Charge Gary Brown of the Westchester Regional Office, under the supervision of Executive Deputy Attorney General for Regional Affairs Martin J. Mack.
Posted in Uncategorized

County Signs Contracts with Childrens Museum and Sustainable Playland. No Terms Disclosed. Board of Legislators In Dark on Financials. Ice Casino Will Not Open Until NEXT July

Hits: 189

WPCNR COUNTY CLARION-LEDGER. By John F. Bailey. July 23, 2013 UPDATED July 25, 2013:

Westchester County Executive Robert P. Astorino signed two contracts today (Asset Management Agreements) with the holding company, Sustainable Playland, and the Westchester Childrens Museum in a news conference at Playland, without disclosing terms of the agreements. Substantial changes to the park will not be made to the park in 2014, but will be delayed for a few years, Mr. Astorino said.

The Sustainable Playland contract  in Mr. Astorino’s view makes final the choice of Sustainable Playland, pending approval by the County Board of Legislators of the Sustainable Playland “Park Improvement Plan,” by January 1.

That is the deadline that Mr. Astorino set for the legislature to act on whether or not they approve of the  Sustainable Playland proposal. At that point, if the Sustainable plan, which  Kim Morque, president of SPI., was in the process of being finalized and submitted to the Board of Legislators.

Astorino said if the Board did not act and approve the Park Improvement Plan , Sustrainable Playland has the right to walk away from the agreement, after January 1.

IMG_5950

Mr. Morque, the Sustainable head, (above, center) answering a question from WPCNR at the news conference as to whether Playland would be open next year and when construction would start indicated the public should not expect too much. He did say that Sustainable has commitments of major financing from  Playland Sports who will build the field house; American Skating who will run the ice casino, Central Amusements International (one of the original responders seeking to run the park, in addition to Sustainable Playland.) To his right is Corinne Zola, President of  Westchester Childrens Museum and, to Mr. Morque’s left, County Executive Robert P. Astorino.

Marque, responding to when work would start said,   “The plan will be submitted within 30 days. It’s a plan that will also evolve. I think there’s perception on the part of the public that on October 1 bulldozers would show up for work, and that’s not the case. We’re going to be very sensitive. We understand the importance of the amusement park components  and keeping a vibrant amusement park so that it’s a great amusement park on a seasonal basis and we think we can do that. We need more open space and a better integration. So we’re excited about it and will be submitting it within 30 days.”

Mr. Astorino, sounding pained, added, “I think that’s a good point. This is…come May of next year will not be a brand-new park This will evolve over several years. People will start to see the park being freshened up, new plantings, painting– all the historical aspect of this will stay. That was very important to all of us. Playland since 1928 has been an art deco feature and that’s what we want to continue. That’s what the public expects. But that doesn’t mean things can’t improve. And they must improve. The public will see some changes, but in the years to come you’ll start seeing bigger and better things happen here: The beginnings of the great lawn, moving things around a bit, maybe some of the oudoor fields. But things take time. I think the important thing is to get the management team in here the professionals in here where they can start making improvements and the county starts making some money so the taxpayers get some relief. That would be the first step. You’ll see some visible signs next year, but as we progress you’ll start to see more and more things, including restaurants being added, some new rides coming in, field house those are the kind of things that will take time.”

Astorino disclosed for the first time that the Playland Ice Casino repairs would not be completed until July of next year, meaning a another dark year for the rink. Astorino said bids for the repair would be opened this week. George Oros a member of the Astorino staff said it was due to the fact the funding was being reimbursed by federal disaster money that has taken months for the county to ascertain whether its availble. Last January the county had decided to go ahead with repairs and hope for reimbursement.

On Thursday, asked for a statement on why it has taken 7 months for the bid process to be completed and work not started, Deputy Communications Director, Donna Greene issued this statement:

“As far as why it took so long, this kind of process always takes time, the design, writing bid specs, advertising, etc.”

Greene said there was no decision on the winning bid as of late yesterday afternoon.

Kenneth Jenkins, the Chairman of the Board of Legislators, told WPCNR in an interview after the conference that the Board would not be rushed into a fast approval of the Park Improvement Plan by January 1. He vowed not to drop his lawsuit, a request for a summary judgment as to whether the County Executive entering into a 10 year licensing agreement was legal without Board of Legislators approval. He also said he was disturbed that today was the first time the administration had informed of the delay in the rink repair. Jenkins speculated the administration delayed the repairs so the skating vendor chosen by Sustainable Playland could execute the repairs the way they wanted.

He also said he liked that Central Amusements International was the Sustainable choice to do the amusement park portion of the park. Jenkins also said the Board had not received copies of the new contracts and had no idea of the financials as to how Sustainable sees their version of the park making money, what rides fees and attractions fees would be and the financial commitments of the backers.

Jenkins said Sustainable had no money of its own to invest, describing them as “a holding company” with the cost of the $34 Million coming from their “partners.” Jenkins said it was his understanding that if Sustainable does not make the money expected, the county gets nothing, and loses $15 Million a year in revenue which the park makes now.

The Children’s Museum Exective Director, Tracy Kay, told WPCNR The Childrens Museum whose contract was also signed today said the museum expected to financer some $10 Million in construction costs against fund-raising leverage to get construction started soon  Kay said the museum would install $6.1 Million of heating ventilation and air conditioning equipment plus $3.8 Million for interior attractions in the museum.

 

Posted in Uncategorized

Noam Bramson Tour Visits White Plains

Hits: 377

WPCNR CAMPAIGN 2013. By John F. Bailey. July 23, 2013:

NOAM BRAMSON, Mayor of New Rochelle, and candidate for County Executive vistited White Plains Monday evening, taking his message to WP to about 30 persons at the YWCA.  About ten of those 30 were political officer holders, including Mayor Tom Roach of White Plains and 4 White Plains Councilpersons, and State Senator George Latimer, and Assemblyman David Buchwald.

HE PRESENTED WHAT HE THOUGHT  WAS WRONG ABOUT THE ASTORINO ADMINISTRATION HOUSING SETTLEMENT POSITIONS.

HE POINTED OUT HOW HE FELT THE COUNTY EXECUTIVE MISREPRESENTED WHAT THE HUD ( DEPART OF HOUSING AND URBAN DEVELOPMENT) HOUSING SETTLEMENT WOULD COST THE COUNTY, HOW MANY UNITS THE COUNTY WOULD HAVE TO BUILD, AND  CHIDED MR. ASTORINO FOR SAYING HUD WAS CALLING FOR REMOVING LOCAL ZONING.

INSTEAD BRAMSON SAID HUD WAS CALLING FOR COLLABORATIVE DISCUSSIONS ON ZONING THAT RESPECTS THE RESTRAINTS PUT UPON COMMUNITIES.

Bramson, speaking with an articulate, compelling freshness of style charged he current County Executive “had not demonstrated constructive leadership when it comes to resolving the affordable housing settlement and enabling us to move on, accusing him of engaging in “a campaign of significant public deception.”

Bramson promised that when the HUD housing crisis was resolved he would work for a “new comprehensive housing policy,” to provide housing for workforce families and young professionals.

He criticized the present administration for a lack of planning and having NO coherent development plan to bring business to the county, criticising how the County Planning Department had been gutted and Westchester has refused to participate in area sustainbability alliances.

He defended   the rate of tax increase in New Rochelle as being the lowest among big cities of Westchester, and touted the New Rochelle municipal tax rate as the lowest in Westchester. He did not answer a question about how much taxes had gone up when asked.

For the record, the New Rochelle city website, http://newrochelleny.com/DocumentCenter/View/696   Document Center reports that in the 10 years between 2003 and 2013, when Mr. Bramson was on the city council and in 2007, becoming Mayor, the New Rochelle CityTax Rate went from $107.14 per $1,000 to $198.50 per $1,000, a tax increase of 85%. The year Mr. Bramson became Mayor (2007) the tax rate was $139.81 per thousand and six years later it is $198.50 per thousand, a 39% increase.  The White Plains Tax Rate for 2013 is $191.74 per thousand dollars of assessed valuation, compared to $198.50  New Rochelle.

The Consumer Price Index for the New York Metropolitan area increased 27% from 2003 to 2013.

 Mr. Bramson accused the County Executive  borrowing 90 Million over the last four years, $48 million in the last year.  He said this  drawing down of fund balance was how Astorino had prevented tax increases.

He said he would create a framework to create savings on services by sharing expenses.  He did not say if he would raise taxes to cover the shortfalls filled by taking county fund balance.

ON THE PLAYLAND SITUATION, HE DID NOT ENDORSE ANY ORGANIZATIONS TO TAKE OVER PLAYLAND. HE BLAMED LOWERING ATTENDANCE ON THE SHARPLY INCREASED ADMISSIONS POLICIES OVER THE LAST FOUR YEARS.

HE SAID PLAYLAND WAS ACTUALLY BREAKING EVEN IF YOU TOOK THE DEBT SERVICE CHARGED THE PARK OUT OF THE NUMBERS. HE SAID THE COUNTY ADMINISTRATION, AND BY INFERENCE THE BOARD OF LEGISLATORS HAD NOT VETTED THE SUSTAINABLE PLAYLAND PROPOSAL WELL. INDICATING THAT HE IS SIMPLY AGAINST THE SUSTAINABLE PLAYLAND PROPOSAL ABOUT TO BE ENTERED INTO IN A CONTRACT WITH THE COUNTY TODAY

He stood for strengthening families

HE SAID HE WANTED TO REORGANIZE THE DEPARTMENT OF SOCIAL SERVICES TO SAVE MONEY AND MAKE A ONE PORTAL DELIVES ALL TYPE EXPERIENCE FOR THOSE USING THE DEPARTMENT.   HE SAID METRICS OF PERFORMANCE SHOULD BE APPLIED TO EVALUATE PERFORMANCES IN ALL DEPARTMENTS. He says this WILL DELIVER A BETTER FORM OF GOVERNMENT.

HE ACCUSED THE PRESENT ADMINISTRATION OF APPLYING A MEAT CLEAVER TO SAVING MONEY ON SERVICES…SUCH AS ITS CUTS ON CHILD CARE.

HE  SAYS THE ADMINISTRATION APPROACH SEEMS TO ALL “SPRING FROM AN IDEOLOGICAL PREDISPOSITION AGAINST PUBLIC ACTION WHICH REALLY BELIEVES THE LESS WE DO TOGETHER THE BETTER OFF WE’LL BE AND THE MORE WE’RE LEFT TO FEND FOR OURSELVES THE BETTER OFF WE’LL BE.”

He said THE ATTITUDE ON THE NINTH FLOOR OF THE COUNTY OFFICE BUILDING TODAY IS “IT’S NOT MY PROBLEM,” AND SAID, “I THINK WE HAVE MORE OF A SENSE OF COMMON PURPOSE THAN THEY DO NOW.”

HE  SAID HIS SUPPORT OF ABORTION (MR. ASTORINO IS AGAINST ABORTION), IS IMPORTANT TO CONSIDER BECAUSE IT ENTERS INTO POLICY MAKING, POINTING OUT THAT ASTORINIO VETOED AN  (ABORTION)  CLINIC ACCESS ASSURANCE BILL AT THE COUNTY LEVEL.

BRAMSON WRAPPED UP HIS TALK SAYING OF COUNTY EXECUTIVE ROBERT ASTORINO,

“HE CAMPAIGNS A LOT LIKE NELSON ROCKEFELLER, BUT WHEN YOU ACTUALLY LOOK AT HIS GOVERNING AGENDA, IT RESEMBLES WHAT YOU MIGHT EXPECT FROM NEWT GINGRICH. THAT IS NOT WHAT LOTS OF PEOPLE BARGAINED FOR WHEN THEY ELECTED HIM FOUR YEARS AGO. I THINK WE NEED A SIGNIFICANT CHANGE.”

Posted in Uncategorized

County Exec to Sign Asset Management Agreement with Sustainable Playland to Develop Playland Tuesday. PREMATURE SAYS BOARD OF LEGISLATORS

Hits: 394

WPCNR PLAYLAND NEWS. From the Westchester County Department of Communications and the County Board of Legislators Press Office. July 22, 1013:

Westchester County Executive Robert P. Astorino will sign two major Playland agreements on Tuesday, July 23, that are designed to preserve the Dragon Coaster and other iconic rides, protect taxpayers and position the 100-acre park in Rye as a year-round destination for family fun.

The County Board of Legislators spokesman, Tom Staudter, said the signing was “premature,” in that the Chairman of the Board of Legislators, Kenneth Jenkins, has a lawsuit pending that the awarding of the contract was not legal for the Board of Acquisitions and Contracts to do without approval of the Board of legislators because of the size of the contract.

Staudter said the proposed signing did not indicate the Board of Legislators had decided that Sustainable Playland was the Board’s choice. He said the Board has retained an independent consultant to evaluate the proposed financial benefits to the county of the four main proposals, including Sustainable Playland are. Staudter said that report would be released “soon.”  Staudter also asked rhetorically if Sustainable Playland would be presenting a check towards the county debt on Playland, (original proposal by Sustainable said they woud present a $4 Million payment for the county Playland debt upon signing of the Assest Management Agreement).

Geoffrey Thompson, spokesman for Sustainable Playland told WPCNR that Sustainable Playland would not present a check to the county at the scheduled signing tomorrow.

Thompson told WPCNR that once the agreement was signed, Sustainable Playland could be free to ink investors in the project to contracts to fund the $34 Million in investment Sustainable Playland promises and proceed. Staudter, the Board of Legislators spokes person said Sustainable financing and ability to fund what they say they will do in Playland was a primary concern of the Board of Legislators.

Staudter pointed out to WPCNR that Sustainable as part of the Asset Management contract, had to provide an “improvement program” by the end of the year, with specifics, for the board approval. He also noted that the courts could very well throw out the Board of Acquisition and Contracts  award of the Asset Management Program to Sustainable.

The signing ceremony will take place on the Playland Boardwalk at 11 a.m. (In the event of rain, the ceremony will be inside the Westchester Children’s Museum’s new home on the Boardwalk.)  Astorino will be joined by Corinne Zola, president of the museum, and by Kim Morque, president of SPI.

  • Astorino will sign an asset management agreement for Sustainable Playland Inc. (SPI) to operate the park. Terms call for SPI to invest $34 million in the park and manage all vendors.
  • Astorino will also sign the lease with the Westchester Children’s Museum for the museum to use one of the renovated bathhouses on Playland’s boardwalk as its home. As part of the agreement, the children’s museum will operate under the umbrella of SPI.

Astorino said both agreements were important components of his initiative to “reinvent Playland for the 21st century,” an effort he began in 2010 upon taking office.

“Since 1928, Playland has been part of the identity and fabric of Westchester County,” said Astorino. “Through our new public-private partnership with Sustainable Playland and the Westchester Children’s Museum, we are reinventing Playland with a vision that builds on tradition by keeping what we love, such as Kiddyland and the historic rides, replaces tax dollars with private capital and adds new attractions and experiences for visitors to enjoy on a year round basis.  This is a winning formula for saving Playland today and for future generations.”

Both Morque and Zola expressed their eagerness to get started on the reinvention of Playland.

“Sustainable Playland is gratified that we have reached this milestone,” said Morque. “We thank our supporters and we look forward to working with the county government, our operating partners, stakeholders and the non-profit community in a public-private partnership that will result in a revitalized park that preserves and enhances Playland’s amusement park components, historic structures and landscapes. We are particularly pleased that the Westchester Children’s Museum will be moving forward with construction of their facility and working with Sustainable Playland in this exciting community-based park restoration effort.”

Zola thanked the County Executive and Board of Legislators for approving the lease and added: “The Westchester Children’s Museum grew from grass roots to more than 3,000 donors from all municipalities in Westchester. This museum will be an economic driver for the county and an anchor for the redevelopment of PlaylandPark. We look forward to seeing a crowd gathered at the Westchester Children’s Museum in 24 months, when we will cut the ribbon and open the doors to our spectacular museum.”

ABOUT THE ASSET MANAGEMENT AGREEMENT WITH  SPI

This season, Playland will continue to be run by the county, with the plan for SPI to take over next season. Under the agreement, SPI, a Rye-based not-for profit, will run the park, maintain the grounds, and manage the vendors who operate activities on the property. The terms of the 10-year asset management agreement or AMA, which includes a 10-year option to renew, call for SPI to invest $34 million in private capital into the park.

In addition, SPI will pay the county a base fee that could eventually total $4 million, provided all zones become operational as planned. SPI will also make annual payments to the county based on the park’s net operating revenue. SPI estimates this to be about $1.2 million per year once the park is fully developed. SPI’s payments will go toward retiring the county’s existing $32 million of debt on Playland.

With the signing, SPI has 30 days to submit a Playland Improvement Plan (PIP) to Astorino, consisting of the material changes the group proposes to make when the park comes under its management. After the PIP is reviewed by the county executive, it will go to the Board of Legislators for approval. If the BOL does not approve the PIP by December 31, 2013, SPI has the right to withdraw from the agreement.

Admission to the park will be free all year round as well as access to Edith Read Sanctuary, the Boardwalk and the Pier. Throughout the park, attractions will be grouped into a variety of zones with fees charged for various activities.

SPI’s proposal includes:

  • An aqua zone, featuring a mini-water park and beach attractions
  • Outdoor ball fields and an indoor field house
  • Renovated indoor ice rink and a new outdoor winter rink
  • A Great Lawn, that will provide enhanced public access to the Long Island Sound and add attractive multi-use space to the park.
  • Indoor multi-use facility, which can be rented for parties, weddings, meetings and conferences
  • New restaurants.

Proceeds to pay the county, maintain the grounds and make improvements will come from fees SPI charges its vendors, equity investments made by SPI and its vendors, revenues generated by the attractions run by the vendors, and other sources of income, such as parking and sponsorships.

SPI was selected by Astorino in 2012, following a “request for proposals” process.  Out of the 12 proposals reviewed by the county and a citizens committee, Astorino said Sustainable was chosen because it had the best vision for the park financially and operationally, as well as far-reaching experience and strong local ties.

The park has been costing taxpayers $3 million to $5 million annually in recent years, as the number of visitors has decreased from over one million in 2006 to 433,000 last year. Under the SPI’s operation, the goal is to make the park a year-round destination, less dependent on weather and to reduce or eliminate the taxpayer subsidy.

ABOUT THE WESTCHESTER CHILDREN’S MUSEUM LEASE

Under terms of the lease approved previously by the Board of Legislators and the Board of Acquisition and Contract, the Westchester Children’s Museum will lease approximately 21,390 square feet of space in what was formerly used as a men’s bath house. The lease will run for 10 years.

The Westchester Children’s Museum, a not-for-profit, will operate under the management umbrella of SPI, which will allow the two organizations to share expertise, minimize costs and increase efficiencies. In return for investing over $7 million in infrastructure improvements, the museum is being given a lease of  $1 a year for a 10-year period. Plans call for the museum to be open to the public within two years.

The Westchester Children’s Museum will be a celebration of childhood. Exhibit areas will contain experiential laboratories, interactive art pieces, sculptural elements, hidden worlds, climbing structures, and physical connections to the outdoors. The museum’s exhibits and programs will draw from the region’s rich history, cultural diversity, flourishing ecosystems, and literary and artistic traditions.

Even before the museum doors open, the Westchester Children’s Museum is delivering quality educational enrichment programs that leverage hands-on, exploratory approaches toward learning.  Its Museum Without Walls programs are presented at a variety of community centers, schools, and childcare centers throughout WestchesterCounty.  Since the program began in 2010, more than 8,000 kids have engaged in learning experiences that are full of fun and discovery.

The Westchester Children’s Museum projects it will add over $4 million a year to the local economy while creating much needed construction and permanent jobs, encouraging tourism, and reinvigorating Playland – all while preserving a national historic landmark.

Posted in Uncategorized