WPCNR SCHOOL DAYS. July 22,2009: The Board of Education authorized the expenditure of $862,636 for rehabilitation of the White Plains High School tennis courts Monday evening.

The tennis courts at the high school will be completely reconstructed beginning in August, anticipated to be completed by Spring 2010. The courts had in the past been considered as the site of a new field house for the high school.

The Board appointed Lisa Panaro, long-time language instructor at White Plains High School to the position of Interim Coordinator for the Language Other Than English program, created this spring to bring language to the Highlands Middle School.
The District also approved payment of $304,500 to Kaiser, Garment & Davidson, its architect for the $69 Million capital improvement project , in commissions for $3.4 Million of new projects that will be undertaken using bond issue money still available from the district Capital Improvement Program.
The Board reinstated six Teaching Assistants from the Preferred Eligible List, bringing the number of Teaching Assistants laid off from 20 down to 14, according to the School District Business Office because some staff have retired, others have taken maternity leaves, others have left the district for other jobs, allowing Teaching Assistants to be brought back on the payroll, and remaining on budget.

The cost of the tennis court construction is $862,636 to repair the tennis court surfaces of 11 high school tennis courts. Each of the 11 courts is laced with cracks and upheaves in the surface (illustrated in the above photograph). The funding is coming from the funds not used from the ongoing bonded capital project coming in under budget that included construction of Post Road School.
Included in the tennis court construction cost is $172,803 for asbestos-contaminated concrete, that Kaeyer Garment & Davidson’s Russ Davidson says has not been a health threat because the asbestos is under the surface.
The tennis team is expected to find courts elsewhere in the city to play.
The board also approved $28,000 for limestone maintenance at Highlands; $30,600 for air-conditioning the computer server room at White Plains High School; $43,704 for a fire pump to maintain pressure for the sprinkler system at the new Post Road School.

Original Model of Loucks Field 2002 –showing new dressing room facilities (gray side structure).
It should be noted that though the new $5.4 Million Loucks Field looks great and plays great, dressing for a game is still going to be done in the cramped, antiquated cinderblockhouse locker room the stadium has had for years. It had been estimated previously at the time the new stadium was being considered for the bond issue that adding new locker room facilities to the new Loucks Field renovation would have cost about $500,000 five years ago. The stadium was refurbished with synthetic turf, lights, and new aluminum bleachers seating 5,000 in hopes of attracting state competitions, but it was built without any improvements to the locker and dressing room facilities.
About ten years ago,the tennis courts had beenconsidered a possible location for a new White Plains High School Field House. Should that project ever be resurrected another spot on the campus would have to be considered.