12 hours go by — 67,811 Con Ed County Customers Out — ONE Crew for WP

WPCNR THE POWER NEWS. March 15,2010: As the forecast for windy10 to 30 mile per hour conditions threatened more tree fellings, Monday morning  as Westchester approachs 12 noon, there are 67,811Con Edison customers without power.


The City of White Plains Communications Director Antoinette Biordi said that Con Edison has advised the city White Plains will be restored by Thursday and the remainder of the city on Friday.


Ms. Biordi said Con Edison has not responded to Mayor Adam Bradley’s pleas yesterday afternoon for more than the one Con Edison wire removal crew currently assigned to the city. “The DPW is right behind the crew,” on their wire clearance process through the city, Biordi told WPCNR, “it takes hours.”


Con Edison announced they will be distributing dry ice in the Saxon Woods Pool parking lot on Mamaroneck Avenue beginning at 12 noon. Residents can use the dry ice to place in their refrigerators to preserve food supplies.


According to the Con Edison Storm Center status grid, the four communities hardest hit at noon continue to be Yonkers, 12,016 out; Greenburgh, 10,289; New Rochelle, 7,732; and White Plains, 6,691.


In White Plains, 697 customers were restored overnight since 11 P.M. Sunday night.


Con Edison announced they will be distributing dry ice in the Saxon Woods Pool parking lot on Mamaroneck Avenue beginning at 12 noon. Residents can use the dry ice to place in their refrigerators to preserve food supplies.


Elsewhere, residents have been piling into local hotels as their homes are without heat due to the power losses.


Around the county, according to Con Edison’s Storm Center statistics as of 12 noon, almost all of Scarsdale is out, with 6,290 customers afffected; Mamaroneck/Larchmont,3,790; Eastchester, 3,893; Harrison, 3,080; North Castle, 1,464; Mount Pleasant,649; Tarrytown, 1,347; Rye City, 2,269; Port Chester, 1,490; Irvington,2,093;  Hastings,1,659; Ardsley, 763.


 

Posted in Uncategorized

Should Con Ed Be Required to Establish Own Massive Emergency Repair Crews

WPCNR THE POWER SURVEY. March 15, 2010: As the “Storm with No Name” continues to make life miserable for Westchester County, the revelation last night by Con Edison that the out-of-state emergency repair crews they always rely on in the aftermath of devastating storm damage come “when they can” and when the out-of-state emergency crews can come is something that no one knew.


Here was a storm that the Weather Channel, the local Accuweather boys and weather alarmists were saying last Wednesday was going to have high winds and gale force potential, 50 miles per hour at least. 48 hours warning.


Con Edison had well-in-advance warning. The Storm with No Name came in Friday night grew in intensity all day Saturday, damage started piling up across the region by twilight Saturday night and we went from 11,000 customers out at 6 P.M. to 70,000 customers out in Westchester alone by Sunday morning, double the outages experienced four weeks ago in the blizzard.


Early Saturday night Con Edison decided to call in emergency crews from outlying states, which are arriving Monday, 48 hours later. Westchester is supposed to turn on by the end of the week.


However, the crews in the middle west coming in had clear weather the middle of last week. Con Edison told WPCNR late Sunday evening, the emergency crews “were reluctant” to commit their crews to Con Edison and leave their areas unprotected.


Well, the damage done by this storm which flirted with a Force 1 hurricane intensity at times (75 miles per hour sustained winds puts you in the “Big Storm League”) speaks volumes about how awesome in terms of what a Force 2 or Force 3 hurricane would do in the county and the devastation that under the present system, Con Edison and all the emergency crews in surrounding regions would simply not be able to correct for months.


With trees still lying across roads and only one Con Edison crew working White Plains according to the city, it is clear that the policians, the Public Service Commission, the Legislature have to address Con Edison and other power companies inability to handle major disasters efficiently.


Granted Con Edison did a solid job in the blizzard four weeks ago, but the blizzard only blew in the 30 to 35 mile an hour wind range.


It is time that Con Edison got some help. If Con Edison cannot call in Emergency Forces to tidy up fallen live wires in an efficient manner because they do not have relief crews, even when they have 48 hours advance notice, when can they? When will they ever?


What is needed is a force that either Con Edison maintains, or works with fire departments to train the local fire departments to remove the wires, or a division of the National Guard is trained to deploy into hard-hit devastated areas. It is clear that the parocial interests of crews from other states with obvious divided responsibilities cannot respond fast enough to handle emergencies everywhere where power outages are concerned. And this is not a knock on those great guys from Virginia, Pennsylvania, Tennessee who have helped us in the past. This is about the practicality.


What do Mr. and Mrs. White Plains think….and Mr. and Mrs. Westchester, all70,000 customers who are waiting for the sight of relief; the fire departments and Departments of Public Works waiting for a “Con Ed man?” 


Tell the hand-wringing legislators and bureaucrats who are responsible for what passes for “emergency preparedness” that it is time Westchester could handle a large outage a lot faster than they can do under the present system.


ONE crew helping White Plains the last 36 hours as was revealed in yesterday’s city hall meeting in White Plains means you have a system that can’t work when this area is hit with a really big storm.


Tell us what you think in the poll at the right.

Posted in Uncategorized

Emergency Supplemental Crews Reluctant to Send in Repair Teams in Advance

WPCNR THE POWER NEWS. By John F. Bailey. March 15, 2010: In response to a question from WPCNR why, Con Edison had not gotten emergency out-of-state reciprocal aid crews into the metropolitan area in advance when every  weather forecaster was predicting high winds and heavy rains  and 24 hours of strong continued winds approaching gale force almost 48 hours in advance of the storm’s beginning, a Con Edison spokesperson said out of state crews were “reluctant” to release crews to aid Westchester and New York City before they knew their own crews would not be needed.


Alan Drury, Con Edison spokesperson, said Con Edison sent out their first calls for out-of-state crews early Saturday evening when over 11,000 Westchester customers had already lost power after a day of winds that did not let up and got stronger through Saturday evening. As of Sunday morning at 8 A.M., 70,000 Westchester Customers were without power.


Drury said that there would be 210 crews into the area Monday, but he could not commit an extra repair crew to White Plains. He said areas would be assessed Monday morning and would be prioritized as to how many crews would be assigned “based on the sensitivity of the areas.”

Posted in Uncategorized

It’s 11 P.M. E.D.T.: 79,000 Westchester Customers Without Power.

WPCNR THE POWER NEWS. From Con Edison Media Relations. (EDITED) March 14, 2010:


Con Edison crews continue responding to outages caused by a powerful storm that knocked trees and limbs into power lines throughout New York City and Westchester County. Approximately 187,000 customers were affected by the storm, far exceeding the number of outages caused by Hurricane Gloria in 1985, when 110,515 customers lost power.


As of 6 p.m. Sunday evening, the company had restored power to approximately 67,000 customers. Approximately 120,000 customers remained without power: 79,000 in Westchester County, 24,000 in Staten Island, 8,800 in the Bronx, 6,000 in Queens, 2,000 in Brooklyn, and about 100 in Manhattan.


Around Westchester County, of the 79,000 customers reporting outages, the areas with the most customers reporting outages continue to be Yonkers, 11,903; New Rochelle, 8,494; Greenburgh, 8,429; White Plains, 7,388; Mount Vernon, 6,372; Scarsdale, 5,870; Harrison, 4,014,Mamaroneck/Larchmont, 2,566; and Eastchester, 3,763.


Con Edison expects restoration to last throughout the week. The company has been securing mutual aid from utilities in several states, including Ohio, Pennsylvania, Georgia and Massachusetts.


Con Edison has approximately 210 restoration crews now in the field, in addition to other field support personnel clearing roads and trees. The number of restoration crews is expected to grow to 350 tomorrow and 425 on Wednesday as more out-of-state crews arrive.


Con Edison has additional customer service representatives, electrical and construction crews, along with tree-clearing crews working around the clock to respond to customers and power outages that may occur.


Customers are urged to call Con Edison immediately to report any outages at 1-800-75-CONED (1-800-752-6633). Customers can also report power interruptions or service problems at www.conEd.com and on their cell phones and PDAs. When reporting an outage, customers should have their Con Edison account number available, if possible, and report whether their neighbors also have lost power.