WPCNR COUNTY CLARION-LEDGER. February 9, 2012:
County Executive Robert Astorino announced today the county is taking the initiative in clearing and rehabilitating the county-owed Bronx River waterway, devoting approximately $9 Million in county money to clearing the river from obstructions and improving chronic flood areas.
.jpg)
Mayor Tom Roach (left) of White Plains appeared applauding the county initiative which is targeting the Bronx River banks on the portion of the river flowing through White Plains, and in the Fisher Lane flood plain, that Mayor Roach noted turned the North White Plains station parking lot into the lake during Hurricane Irene. The work will be paid for by the county ($700,000), with no cost to the city, part of Astorino’s initiative on mitigating Bronx River flooding announced today.
.jpg)
The work is being done by county park crews along the river north of the County Center, and is being funded south of the County Center by the Army Corps of Engineers at a cost of $1,000,000, which includes $87,000 from the county, and $514,000 in in-kind services from the county, and the National Fish and Wildlife Foundation is funding the East Bank that remains to be done.
.jpg)
West Bank of the Bronx River has been rehabilitated and rerouted. Next will come the shoring up of the East Bank with installation of stone retainer walls (stone blocks piled in upper left await installation) to prevent erosion and silting from rains washing away the banks.The East Bank will cost $700,000 with the County paying $350,000 and the National Fish and Wildlife Foundation, $350,000
The County Executive also announced projects at several other flood prone locations: Raising the Oak Street Pump Station in Mount Vernon/Yonkers, at a cost of $450,000 to $500,000; Bronx River realignment and bank stabilization at Garth Woods, $1,000,000 estimated;Harney Road in Eastchester/Yonkers, bank stabilization and channel modification, estimate not available; in Larchmont, drainage improvement along Pine Brook at Boston Post Road: County cost: $2.3 Million, Village of Larchmont, $2.3 Million; in New Rochelle, replacing the Hutchinson River culvert, $5,000,000 split between the county and New Rochelle.
Astorino said the county owns the Bronx River and therefore can execute rehabiltation projects faster than on properties owned by the state, such as the Saw Mill River Parkway, that he indicated was the state responsibility. “The county can and must do whatever it can on its own. While I will continue meeting with state and federal officials to advocate for assistance, we will do everything we can at the county level, working with our municipalities, to target achievable projects to reduce and prevent future flooding.”
The County Executive told the CitizeNetReporter chronic flooding at the North White Plains railroad station would not be addressed but will be tackled in the future.
The Cloverdale Road area in White Plains, another chronic flooding area in White Plains would not be addressed in this phase. County Legislator Bill Ryan, a resident of Seneca Avenue, told WPCNR, the small capacity of the sewer along Cloverdale Road was overmatched by the flow of water from the marsh east of and adjacent to the Central Westchester Parkway. Ryan giving his opinion only, said the cost of replacing that sewerline would cost well into the millions and would have to involve ripping up just completed construction on I-287. In his opinion, some homes that chronically flood in the Cloverdale area would have to be raised up to a higher level and the homeowners bought out and the area turned into a park to absorb the flooding naturally.
.jpg)