No Plan to Decide BRT Until Input Is In. 60 Experts to Judge Bids. Tolls In Air


WPCNR TAPPAN ZEE BRIDGE NEWS. By John F. Bailey. July 25, 2012. Part 2:


WPCNR provides this wrap-up of the rest of the LoHud Editorial Spotlight discussion with Governor Andrew Cuomo’s Tappan Zee Team. To see the discussion in its entierty go to http://www.livestream.com/editorialspotlight/video?clipId=pla_0d5dea02-9da5-4214-9941-30bdb19206c2&utm_source=lslibrary&utm_medium=ui-thumb:


Optimism for an  increase in funding from the Federal Government was expressed by Thruway Authority Executive Director Thomas Madison, that with new funding passed this year by congress made available for the TIFIA program(Transportation Infrastructure Finance and Innovation Act, the state may be able to fund more with TIFIA than the $2.2 Billion they are asking for now. But this appeared to be wishful thinking, with nothing concrete.


Larry Schwartz, the Secretary to the Governor, said the effect on tolls for the bridge is still being evaluated, expressing the hope the tolls would be comparable to similar bridges in the area.


As an aid, WPCNR calculated in February that to finance $6.2 Billion through the TIFIA program,  at its current rate and pay the maintenance costs of the new bridge, tolls would have to go up to $11.50 a Trip. To read that commentary go to  www.whiteplainscnr.com/article9023.html


No timelines were given as to how soon a decision would be made on the bids from bridge contractors on the costs of building the new bridge.  The Governor’s office is now assembling an evaluation team of about 60 persons, what New York State Thruway Executive Director called “the best and the brightest from around the world,” to evaluate contractor bids due to be submitted tomorrow.


Larry Schwartz, the Secretary to Governor Cuomo said the names of the “Evaluation Team” would be announced by the Governor’s office when they are finalized. It was noted that the Federal Government would also have to approve any construction using Federal money.


Schwartz said that the possibility of using Route 119 as the dedicated bus lane through Westchester County ( long promoted by the Tappan Zee project for Bus Rapid Transit in previous meetings) has not been discarded, but the imput of all communities had to be considered. He noted that Thruway project affecting White Plains at Exits 7 & 8 had dragged 25% longer than it should have taken and the impacts of establishing BRT lanes on 287 would subject that area and its citizens to more inconvenience for years.  


Schwartz returned to the theme of gathering input from communities, decision-makers and government officials, and the need to reach consensus together on how to execute rapid transit through the counties, and to determine the need for it. He did not dismiss the data already gathered by the Thruway Authority engineering teams on transit data.


Brian Conybeare, the newly appointed representative to deliver the message of the administration, said it would be his job to disseminate key information to the public as the Governor’s Office makes decisions. He said the public could ask questions via phone at 1-800-855-TZBRIDGE or go to the new website made live today at www.newnybridge.com


The Governor’s Tappan Zee Bridge Team today gave the impression that indicated months of meetings and discussion lie ahead for the Tappan Zee Bridge Project which to move ahead requires more meetings with more people, scores of government officials and stakeholders in the project.

Posted in Uncategorized

White Plains Sales Tax $$ UP 9.6% At Fiscal Close—


WPCNR QUILL & EYESHADE. By John F. Bailey. July 25, 2012:


 White Plains completed its fiscal year June 30 with a 9.6% real gain in sales receipts, setting an all-time high in sales tax collections of $50,972,671.36, compared to $46,494,447 in 2010-11, a gain of a real 9.6% year to year.


White Plains had been riding a 15% gain in sales tax collections through May, however June receipts were off 15.3% at $4,218,196.45  ($762,780 less than June 2011’s record $4.9Million).


Westchester County Sales Receipts in June, (the halfway mark in the county fiscal year) were off 1.4% which means the county is virtually even with last year’s sales tax collection pace ($230.1 Million to $222,991,747 after six months in 2011.)

Posted in Uncategorized

COUNTY TO COUNTY BRT A LONG WAY OFF. 100 TO 150 COMMUNITY MEETINGS PROMISED

 


WPCNR TAPPAN ZEE NEWS. By John F. Bailey. July 25, 2012:


In a lohud.com webcast that went down after the first twenty minutes due to unexplained technical difficulties, Larry Schwartz, Secretary to Governor Andrew Cuomo, and Thomas Madison , State Thruway Authority Executive Director, made clear that a Tappan Zee Bridge cross-Rockland, cross-Westchester Bus Rapid Transit system will not become reality for years.


The form the BRT lanes promised on the new Tappan Zee Bridge will take after they touch the Rockland and Westchester shores has also not been decided. That massive undertaking will only take shape after the state conducts meetings with community officials all along the route. Schwartz emphasized the state wanted to proceed forward working directly with the communities. This, coming after the New York State Thruway has been involving communities in presentations, drawing up plans and taking their comments the last ten years, as a cost of $280 Million.


The moderator,Nancy Cutler, Lohud Rockland County Opinion Editor, asked directly if there been any decision about whether to extend the promised BRT Lane piecemeal (across Westchester County and Rockland Counties) or across the counties, Schwartz said


 ” I think the commitment is to not make any predertermined decisions but to work with the Rockland County Executive, the Westchester County Executive, their staffs, as well as the local elected officials in the community, the business community, the transit advocates, and the civic associations to figure out what makes sense, what’s needed and what will be used (ridden). “


“We’re going to have as many meetings with the community and the different stakeholders here in the lower Hudson Valley region as needed. We’re targeting now between 50 to 100 (meetings), but if we need to do 150, whatever number we need to do, this is an on-going process. Governor Cuomo has made it clear  that he wants the process to be open and transparent now and throughout the construction  phase of the new Tappan Zee Bridge. That’s why we’re here in this ongoing effort to establish an open line of communication, to get input and feedback , to learn to listen, and also to be responsive to the concerns and questions that Westchester and Rockland residents have regarding our building a new Tappan Zee Bridge.”


Schwartz promised to do a better job “in terms of our openness, our transparency, and making sure we have a constructive dialogue.”


He said..”In addition to being transparent, we need to be honest, trustworthy, straightforward  and credible. That’s the governor’s task to me and to the project team here in not making commitments the state will not be able to keep.”


Madison said the build first with transit inclusion was the best solution:  “a brand-new structure that would not preclude any transit option for the future, and this was central to the governor’s vision for moving forward with the Tappan Zee Bridge project: let’s build a bridge now; build a bridge we can afford today, but make the necessary investments today that make a commitment today that in the future we will not preclude any transit option on the bridge.”


Schwartz noted on BRT feasibility:


 “even on an incremental (construction) basis, it’s going to be cost.y that  One of the proposals we presented today was a Suffern to Tarrytown BRT System that would cost $1.9 Billion, depending on how you construct it. SomeBODY has to pay for that. We have to find the money. Governor Cuomo has made it clear we have to move forward with the bridge, and we have to do this project in the most financially feasible and affordable way, that doesn’t have an impact on the taxpayers, and minimizes the impact on the toll-payers. The governor’s committed to transit; he’s certainly committed to transit on the bridge; he’s committed on working on transit solutions off the bridge…there’s a lot of ideas out there some of those ideas are going to have significant community impacts and I think we need to do a better job of  educating and informing the community, when you build a BRT what that really means in terms of not only costs, but community impact. In 1997, they talked about widening I-287 to include HOV (High Occupancy Vehicle) lanes…there was a lot of community outcry from Greenburgh, Elmsford, and White Plains and Governor George Pataki dropped the idea.”


An engineer on the panel Mark Roach, said the key to making BRT a success was reliability which could only come from dedicated bus lanes.


When the complete discussion is available, WPCNR will follow up with more coverage of the rest of the discussion. At the time when the feed went down on Internet Explorer from the lohud site, there were approximately 325 viewers


Tonight at 6 PM at the Performing Arts Center at Purchase College, 735 Anderson Hill Road there will be another forum with state officials to discuss Tappan Zee Bridge issues. Thursday there will be one in Rockland County at the Rockland Community College Cultural Arts Theatre, 145 College Road, Ramapo.

Posted in Uncategorized

Gov Hires News 12’s Conybeare to Liaison on Tappan Zee Bridge. Salary:$160,000

WPCNR TAPPAN ZEE BRIDGE NEWS. From Governor Andrew Cuomo’s Press Office. July 24, 2012 UPDATED JULY 26, 2012:


Governor Andrew M. Cuomo  announced Tuesday the appointment of Brian Conybeare to the position of Special Advisor for the Tappan Zee Bridge. Mr. Conybeare will serve as the liaison for the Governor to Hudson Valley residents and businesses, at a salary of $160,000, according Director of Public Affairs of the New York State Thruway Authority, Dan Weiller, the Albany Times-Union reported Thursday


 As such, he will be located in the Hudson Valley on full time basis conducting the day-to-day meetings with local community and business leaders, and working with Secretary to the Governor Larry Schwartz, who Governor Cuomo recently appointed to oversee the Tappan Zee Bridge project. Mr. Conybeare will play an important role in ensuring that the issues raised by residents involving the $5 billion project are heard and resolved.



“After more than ten years of gridlock surrounding the Tappan Zee Bridge project, we are moving forward to finally build a new, safer bridge for the Hudson Valley,” said Governor Cuomo. “As we continue to make progress, Brian Conybeare will help connect my administration with residents and the business community. Mr. Conybeare has an extraordinary background in journalism and is familiar with the many facets of this complex project. In his role, he will help ensure that affected communities are provided the information they need and that concerns are properly addressed. Together, we will build a bridge that serves all of Hudson Valley.”



Mr. Conybeare said, “I would like to thank Governor Cuomo for giving me the opportunity to participate in this significant project. The New Tappan Zee Bridge will be a testament to New York’s workforce and innovation under Governor Cuomo. I look forward to working with the Governor and his team to ensure that the new bridge is constructed through a transparent and inclusive process.”



Prior to his appointment, Mr. Conybeare was an anchor for the News 12 Evening Edition. He was also a co-anchor on the weekly political talk show “Newsmakers” and hosts the station’s local election debates and live town meetings.



Mr. Conybeare is an award-winning reporter, most recently receiving a 2011 New York Emmy Award for his exclusive story on a parking ticket scam called “Rental Rip-off.” In 2009, Brian won a national award from the Society of Professional Journalists. His ground-breaking reporting on corruption in the promotions department of the Yonkers Raceway Casino led directly to a criminal probe and three arrests. It also won him the highly respected Sigma Delta Chi Award from the SPJ. He has also been honored with two other New York Emmy Awards, five Edward R. Murrow Regional Awards, and five New York Associated Press Broadcast Awards.



Mr. Conybeare received a Bachelor’s Degree in Communications from the University of Michigan and a Master’s Degree in Journalism and Mass Communication from New York University. He currently resides in Eastchester with his wife Janna and their four children.



After ten years of delay, the movement to replace the Tappan Zee Bridge is finally underway under the leadership of Governor Cuomo. The project will build a new bridge that will be safer, transit ready and, in the process, will create over 45,000 jobs. Representatives of the Governor’s office are presenting plans to local communities to receive feedback on the project. Mr. Conybeare’s appointment will help further the dialogue and feedback between the Governor, local business representatives and residents of the Hudson Valley community.